Execute them Latest January 31st or Be Charged For Misappropriation - Hon. Fusi Naamukong


Commercial Avenue Bamenda

Contractors and other stakeholders involved  in the execution  of the    public investment budget in mezam have been given till  january 31st   to consume  pending 2018/19 credit cards of  5million and below, or face charges of misappropriation of public funds.

Member of parliament for bafut/tubah constituency Hon Fusi Naamukong, who doubles as head of the Mezam divisional follow up committee made the remark  jan 15th. at the fourth quaterly follow up meeting, convened to evaluate  the physical and financial realisation of 2019 projects in the division.

 It was observed at the follow up session that there exists  2018 projects  of less than 4million, that have not been executed by  some  project owners  who continue to cite insecurity as reason for their non execution

 while congratulating sub divisions like santa, bamenda III and II for negotiating their way through the realisation of most of their projects, he frowned at sub divisions like tubah for lagging behind.

4th Quarter follow up evaluation session

"The era of citing the crisis in the region as excuse for not doing work  is lazy, and before contractors bidded for these projects they were aware of the insecurity in the region." he added

Meantime the committee also called on the pay master general of the north west  treasury, to pay outstanding bills owed some economic operators so they can be able to pick up new projects.

The news  from the prime minister's office announcing the re-programing of projects not executed in the North West and South West regions of the country oweing to the crisis was also saluted by members of the committee. 

 Other recommendations arrived at the meeting  include:

 - The need for project owners to facilitate and accelerate execution of the 2020 public investment budget,  in strict respect of  the administrative procedures.

- Need for  state control engineers to accomapny the execution process of projects, as to ensure  standard and quality.

- And for warning letters to be served to  contractors who fail  to meet execution deadlines.

Cross section participants at NW budget launch.

Public Investments projects(PIB) which include; municipal road maintenance, construction of boreholes and bridges, infrastructures and supply of school and hospital materials, electrification, construction of markets and community halls etc, are supposed to improve the livelihood of inhabitants of the beneficiary community. 

Their non execution therefore  hampers growth and slows down development.

 Mezam for 2019 had a total of 117 projects. 40 has been completely executed, 39 ongoing, 40 awarded but not touched at all, leaving physical realization at 49.23% with financial engagement at 18.34%.

Comments

Popular posts from this blog

Bali Old Boys Association(BOBA) Celebrates Golden Jubilee, Diamond Jubilee Of CPC Bali in Style

Secondary education ministry lauds efforts of assembly in promoting education in crisis-hit North West

New framework, key innovations of Presidential Plan for Reconstruction and Development detailed to stakeholders in the NW